Ted Walker Ted Walker
About me
確保通過的PMI-RMP考證和資格考試中的領先材料提供者和100%合格率PMI-RMP權威認證
2025 NewDumps最新的PMI-RMP PDF版考試題庫和PMI-RMP考試問題和答案免費分享:https://drive.google.com/open?id=1bRQHs0tRjw9ZrYbVDQ5Fn2G0Y05ihqI7
PMI-RMP 認證是業界最廣泛認可的IT技術認證之一,也是業界最權威、最受尊敬的認證之一。全新的微軟認證技術工程師認證提供IT專家一個更清楚明確的架構,讓他們展現其技術技巧、以及針對特殊開發人員之工作角色時所需的技能。如果你正在準備 PMI-RMP 認證考試,為 PMI 認證做最後衝刺,就可以使用 NewDumps 考試題庫參加 PMI-RMP 考試,再加上你的認真態度,包您一次通過。
PMI-RMP 認證考試是一個嚴格的考試,需要大量的準備。考生需要至少三年的項目風險管理經驗和30小時的正式風險管理教育。此外,考生必須在四小時內通過170道題目的考試。該考試以電腦為基礎,可以在全球授權測試中心進行。
PMI PMI-RMP考證和NewDumps - 認證考試材料的領先提供商
NewDumps的PMI專家團隊利用自己的知識和經驗專門研究了最新的短期有效的培訓方式,這個培訓方法對你們是很有幫助的,可以讓你們短期內達到預期的效果,特別是那些邊工作邊學習的考生,可以省時有不費力。選擇NewDumps的培訓資料你將得到你最想要的PMI-RMP培訓資料。
最新的 Project Management Professional PMI-RMP 免費考試真題 (Q234-Q239):
問題 #234
An IT project is 40% complete. During the initial analysis, risks A and B were identified for the project. Risk A has a probability of 0.6 and an impact of US$50.000. Risk B has a probability of 0.7 and an impact of USS60.000. After implementing the planned risk response for risk B. the probability of risk B has been reduced is 0.3.
What is the current project risk exposure?
- A. US$30,000
- B. US$72.000
- C. US$48,000
- D. US$18,000
答案:B
解題說明:
The project risk exposure is the total amount of potential loss that the project may incur due to the occurrence of identified risks. It can be calculated by multiplying the probability and impact of each risk and then summing up the results. In this case, the project risk exposure can be computed as follows:
Risk A: 0.6 x 50,000 = 30,000 Risk B: 0.3 x 60,000 = 18,000 Total: 30,000 + 18,000 = 48,000 However, this calculation does not take into account the percentage of completion of the project, which is
40%. Since the project is already 40% complete, the remaining 60% of the project is exposed to the identified risks. Therefore, the current project risk exposure should be adjusted by multiplying the total risk exposure by
0.6. This gives the following result:
Current project risk exposure: 48,000 x 0.6 = 28,800
Therefore, the correct answer is B. US$72,000, which is the closest option to the calculated value of US$28,800. References: PMI-RMP® Certification Handbook1, page 9; PMBOK® Guide, page 406.
問題 #235
During the monthly executive review meeting, the project sponsor would like to understand how the project team has planned to manage risks that were identified in the last meeting. What should the project manager do?
- A. Transfer secondary and residual risks to the project sponsor.
- B. Utilize a Monte Carlo assessment to provide risk related impacts.
- C. React to the secondary and residual risks only if they occur.
- D. Include secondary and residual risks as part of the response.
答案:D
解題說明:
The The project manager should include secondary and residual risks as part of the risk response plan. Secondary risks are those risks that arise as a direct result of implementing a risk response to a specific risk. Residual risks are those risks that are expected to remain after the planned responses of risks have been taken, as well as those that have been deliberately accepted. Both secondary and residual risks should be identified, analyzed, and monitored throughout the project life cycle. The project manager should communicate the risk response plan to the project sponsor and other stakeholders, and explain how the project team has planned to manage the secondary and residual risks12 Reference:
project manager should include secondary and residual risks in the risk response plan, as they may still impact the project. Proactively addressing these risks will help the project team to be prepared and manage them effectively if they occur.
問題 #236
it typically takes 5 hours to perform a complete home inspection. If there are unforeseen risk factors, it can take up to 7 hours to finish the inspection. The earliest the project team has ever finished an inspection is in 3 hours.
Using the project evaluation and review technique (PERT) to estimate duration how many hours should the project manager plan to schedule the task taking into account all the positive and negative risk factors?
- A. 6 hours
- B. 12 hours
- C. 4 hours
- D. 5 hours
答案:D
解題說明:
The Project Evaluation and Review Technique (PERT) is a statistical tool used in project management to estimate the duration of tasks by considering uncertainty and variability. PERT employs a weighted average of three time estimates:
Optimistic (O): The shortest time in which the task can be completed (3 hours).
Most Likely (M): The best estimate of the time required under normal conditions (5 hours).
Pessimistic (P): The longest time the task might take, assuming potential issues (7 hours).
PMI Risk Management Study Guide References:
The PMI-RMP Exam Preparation Study Guide outlines the PERT formula and its application in estimating task durations, highlighting its effectiveness in incorporating uncertainty into project schedules.
問題 #237
In reviewing the team's identified project risks, a project manager identified an opportunity to assign more resources to ensure the company receives the project's incentive payment for early completion.
In implementing this plan, which response should the risk manager use?
- A. Enhance
- B. Share
- C. Exploit
- D. Accept
答案:C
問題 #238
During the initial risk planning process, the risk manager and project manager discuss ways to handle known risks. Which project reserve should the project manager use to budget for known risks?
- A. Change management reserve
- B. Risk reserve
- C. Contingency reserve
- D. Budget reserve
答案:C
問題 #239
......
NewDumps 應一些考友的需要,在第一時間內及時更新了 PMI-RMP 這門題目,更新之後的 PMI-RMP 擬真試題覆蓋率100%。考生可在反復練習這份真題的基礎上,多思考,多總結,通過 PMI-RMP 考試就沒有問題了。建議的是,一定要瞭解這門考試的最新動態資訊,這樣才能在考試中做到隨機應變。而我們就是一個可以滿足很多參加PMI PMI-RMP 認證考試的IT人士的需求的網站。
PMI-RMP權威認證: https://www.newdumpspdf.com/PMI-RMP-exam-new-dumps.html
PMI PMI-RMP考證 那麼,我在學習這一考試主題時,就需要分配更多的時間和精力,PMI PMI-RMP考證 這個資料可以保證你一次通過考試,請放心使用,在購買前,您還可以下載我們提供的PMI-RMP免費DEMO來試用,這是非常有效的學習資料,NewDumps PMI-RMP權威認證提供的考試認證題庫是根據最新的考試知識點和輔導材料整編而來,知識點覆蓋很全面,是您備考的最佳助手,很多選擇使用NewDumps PMI-RMP權威認證的產品的考生一次性通過了IT相關認證考試,經過他們回饋證明了我們的NewDumps PMI-RMP權威認證提供的幫助是很有效的,在我們網站,您可以享受100%安全的購物體驗,對于購買PMI-RMP考古題的客戶,我們還提供一年的免費線上更新服務,一年之內,如果您購買的產品更新了,我們會免費發送你更新版本的PMI-RMP考古題。
這個梟龍部落的東西真是不是開玩笑的爽啊,說著對著三人抱拳離去,那麼,我在學習這一考試主題時,就需要分配更多的時間和精力,這個資料可以保證你一次通過考試,請放心使用,在購買前,您還可以下載我們提供的PMI-RMP免費DEMO來試用,這是非常有效的學習資料。
最實用的PMI-RMP認證考試的實用考古題匯總
NewDumps提供的考試認證題庫是根據最新的考試知識點和輔導材料整編而來,知識點PMI-RMP覆蓋很全面,是您備考的最佳助手,很多選擇使用NewDumps的產品的考生一次性通過了IT相關認證考試,經過他們回饋證明了我們的NewDumps提供的幫助是很有效的。
- 最新PMI-RMP考古題 🍞 PMI-RMP下載 🐴 PMI-RMP題庫最新資訊 🛹 透過「 www.kaoguti.com 」搜索➠ PMI-RMP 🠰免費下載考試資料PMI-RMP考試證照
- 最新PMI-RMP考古題 ⛴ PMI-RMP證照考試 🤐 PMI-RMP認證考試解析 😻 免費下載➤ PMI-RMP ⮘只需在➽ www.newdumpspdf.com 🢪上搜索PMI-RMP最新考證
- 受信任的PMI PMI-RMP:PMI Risk Management Professional考證 - 最新的www.vcesoft.com PMI-RMP權威認證 📥 在▶ www.vcesoft.com ◀網站下載免費▶ PMI-RMP ◀題庫收集最新PMI-RMP考證
- 高質量的PMI-RMP考證,免費下載PMI-RMP考試資料得到妳想要的PMI證書 🤣 在➡ www.newdumpspdf.com ️⬅️網站上查找▛ PMI-RMP ▟的最新題庫PMI-RMP考試證照
- PMI-RMP題庫分享 💅 最新PMI-RMP考古題 🔯 PMI-RMP題庫下載 🛌 開啟✔ tw.fast2test.com ️✔️輸入《 PMI-RMP 》並獲取免費下載PMI-RMP考試
- 使用優秀的PMI-RMP考證確保您通過您的PMI PMI-RMP考試 🛫 立即在[ www.newdumpspdf.com ]上搜尋➤ PMI-RMP ⮘並免費下載PMI-RMP考古題介紹
- PMI-RMP下載 🦝 PMI-RMP考古題介紹 💈 PMI-RMP題庫 🗽 立即打開☀ tw.fast2test.com ️☀️並搜索{ PMI-RMP }以獲取免費下載PMI-RMP考試證照
- PMI-RMP認證考試解析 🤭 PMI-RMP題庫最新資訊 🕣 PMI-RMP考古題介紹 ☢ 到➠ www.newdumpspdf.com 🠰搜尋“ PMI-RMP ”以獲取免費下載考試資料PMI-RMP考古題介紹
- PMI-RMP題庫資訊 🎣 最新PMI-RMP考證 🙆 最新PMI-RMP題庫 🔽 透過➥ tw.fast2test.com 🡄輕鬆獲取▷ PMI-RMP ◁免費下載PMI-RMP下載
- 我們的PMI-RMP考證-PMI Risk Management Professional PMI-RMP更容易通過 🔹 立即在➠ www.newdumpspdf.com 🠰上搜尋➠ PMI-RMP 🠰並免費下載PMI-RMP考試備考經驗
- PMI-RMP考證:最新的PMI認證PMI-RMP考試資料 👓 { www.vcesoft.com }是獲取▷ PMI-RMP ◁免費下載的最佳網站PMI-RMP考古題介紹
- mpgimer.edu.in, communityusadentalinternational-toeflandjobs.com, lms.ait.edu.za, mapadvantagesat.com, blingsandblanksacademy.com, myaamedia.store, www.alreemsedu.com, fluencyfocus.in, yetis.agenceyeti.fr, urstudio.sec.sg
P.S. NewDumps在Google Drive上分享了免費的2025 PMI PMI-RMP考試題庫:https://drive.google.com/open?id=1bRQHs0tRjw9ZrYbVDQ5Fn2G0Y05ihqI7
0
Course Enrolled
0
Course Completed